Is there a reason why AMS (presumably the IXs)?

You may find other NL DCs cheaper but still close enough to AMS for your needs. 
For example, in Rotterdam there has been more investment in the port's 
industrial grid infra, which may get you a cheaper rate for power.

In any case, the rate you have been quoted seems high and you can definitely 
shop around.
On Wednesday, 11 December 2024 at 19:45, harbor235 <harbor...@gmail.com> wrote:

> Hi all,
>
> Looking for colo space in Amsterdam, is it common to have to pay for phase3 
> power busbar and busbar, power supply, and tap off? Total costs for adding 3 
> phase plus testing etc ..... 136.000 Euros for NRCs and the following MRC:
>
> The Service Fee for a 20kW deployment would be €350/kW/month, so €7,000 per 
> month in total based on a 36 month term and 3% annual indexation
>
> ·Electricity consumption will be measured and invoiced monthly in arrears at 
> €0.278 per kWh (2024 pricing)
>
> Mike