Hi all,
Looking for colo space in Amsterdam, is it common to have to pay for
phase3 power busbar and busbar, power supply, and tap off? Total costs
for adding 3 phase plus testing etc ..... 136.000 Euros for NRCs and
the following MRC:
The Service Fee for a 20kW deployment would be €350/kW/month, so €7,000
per month in total based on a 36 month term and 3% annual indexation
· Electricity consumption will be measured and invoiced monthly
in arrears at €0.278 per kWh (2024 pricing)