Yea, looks like whoever did that quote does not really want the business and is 
pricing it as such

 

From: NANOG <nanog-bounces+tony=wicks.co...@nanog.org> On Behalf Of Aaron Wendel
Sent: Thursday, 12 December 2024 8:05 am
To: harbor235 <harbor...@gmail.com>; NANOG list <nanog@nanog.org>
Subject: Re: COLO space in EU

 

So they have a charge just to have the capacity present of 7000 euros/month and 
then .278 euros per KWh on top of that?

 

I wish I could get away with charging that.

 

Aaron

 

 

 

------ Original Message ------

>From "harbor235" <harbor...@gmail.com <mailto:harbor...@gmail.com> >

To "NANOG list" <nanog@nanog.org <mailto:nanog@nanog.org> >

Date 12/11/2024 12:45:52 PM

Subject COLO space in EU

 

Hi all,

 

Looking for colo space in Amsterdam, is it common to have to pay for phase3 
power busbar and busbar, power supply, and tap off?  Total costs for adding 3 
phase plus testing etc ..... 136.000 Euros for NRCs and the following MRC:

 

The Service Fee for a 20kW deployment would be €350/kW/month, so €7,000 per 
month in total based on a 36 month term and 3% annual indexation

*        Electricity consumption will be measured and invoiced monthly in 
arrears at €0.278 per kWh (2024 pricing)

 

Mike

 

 