+1 for the release plan. Thanks!

+1 for releasing 4.0 four months after 3.9. 4.0 is actually a pretty big
release as we will GA KIP-848, including new group coordinator and new
consumer rebalance protocol. This is a pretty big change :).

Best,
David

Le lun. 17 juin 2024 à 20:36, Colin McCabe <cmcc...@apache.org> a écrit :

> Hi all,
>
> Thanks, everyone.
>
> Quick update: on the release plan page, I moved feature freeze forward and
> code freeze by one week to make sure we can hit that. No other dates
> changed.
>
> With regard to 4.0, I was assuming that we'd do it 4 months after 3.9 was
> released. I think for that release, we should front-load all the "remove
> deprecated stuff" work that has piled up, and try to really hit all the
> release milestone dates. I don't think 4.0 needs to be a very ambitious
> release, it really is mostly about the removals and the new JDK (which are
> a big deal, but I hope should fit within the normal timeframes). That being
> said, if people want a shorter 4.0, I'm open to that, as long as we're
> confident we could actually do that :)
>
> best,
> Colin
>
>
> On Fri, Jun 14, 2024, at 20:56, Sophie Blee-Goldman wrote:
> > +1, thank you Colin
> >
> > Given the July freeze deadlines, I take it we are going with the "short
> > 3.9.0 release" option and that the existence of this release will impact
> > the 4.0.0 deadlines which will still follow the usual schedule -- in
> other
> > words, this is an "additional release" outside of the regular timeline.
> Is
> > this understanding correct?
> >
> > On Fri, Jun 14, 2024 at 5:57 PM Chia-Ping Tsai <chia7...@gmail.com>
> wrote:
> >
> >> +1 thanks Colin!
> >>
>

Reply via email to