Eric, that sounds about right, just add the IP addresses and should be good
to go.

On Sat, Jul 4, 2009 at 10:22 AM, Eric Stanfield <[email protected]>wrote:

>  Must be time to re-up the caffeine levels…
>
>
>
> That’s the only thing I’ve noticed so far that I haven’t been able to chalk
> up to the PG doing something one way and me doing it another.
>
>
>
> So that I can run that lab tomorrow morning again – do I just need to
> complete the other side of those routed links?
>
>
>
> For today I bagged it and loaded up a different one.
>
>
>
> *From:* Bryan Bartik [mailto:[email protected]]
> *Sent:* Saturday, July 04, 2009 11:18 AM
>
> *To:* [email protected]
> *Cc:* [email protected]
> *Subject:* Re: [OSL | CCIE_RS] workbook 1 lab 9 - cat addressing
>
>
>
> Ah, ok. You had lab 9 in the Subject heading :) Looks like the addresses
> need to be added to the initial configs. Is there any other discrepancies
> you have seen?
>
> On Sat, Jul 4, 2009 at 10:10 AM, Eric Stanfield <[email protected]>
> wrote:
>
> Workbook v10 Volume 1 Task 11.7, starting on page 317 in the PG.
>
>
>
> *From:* Bryan Bartik [mailto:[email protected]]
> *Sent:* Saturday, July 04, 2009 11:03 AM
> *To:* [email protected]
> *Cc:* [email protected]
> *Subject:* Re: [OSL | CCIE_RS] workbook 1 lab 9 - cat addressing
>
>
>
> Eric, what volume is this? What page of the PG are you looking at?
>
> Thanks,
>
> On Sat, Jul 4, 2009 at 9:51 AM, Eric Stanfield <[email protected]>
> wrote:
>
> Apologies if I am again missing something written in the guide, but I can't
> seem to find any indication of what interfaces should be built on the 4
> switches in order to peer them together in as10101.  When I load the
> configs
> into the proctorlabs rack, cat1 has a svi in 150.100.81.0/24 with which it
> can later peer with R8 and then a handful of routed interfaces which appear
> to be one side of routed links to the other three cats.  Cat2 has no l3
> interfaces until the 200.x.x.x loopbacks are created.  Cat3 and Cat4 have
> no
> l3 interfaces at all.
>
> The PG shows Cat2/3/4 being configured with network commands referencing
> the
> subnets shown in the bottom right of diagram 1.  Is this some unspoken task
> of having to finalize the routed link configs on Cat2/3/4 or am I just
> missing something obvious.
>
> Thanks
>
>
>
>
> --
> Bryan Bartik
> CCIE #23707 (R&S), CCNP
> Sr. Support Engineer - IPexpert, Inc.
> URL: http://www.IPexpert.com
>
>
>
>
> --
> Bryan Bartik
> CCIE #23707 (R&S), CCNP
> Sr. Support Engineer - IPexpert, Inc.
> URL: http://www.IPexpert.com
>



-- 
Bryan Bartik
CCIE #23707 (R&S), CCNP
Sr. Support Engineer - IPexpert, Inc.
URL: http://www.IPexpert.com

Reply via email to