Workbook v10 Volume 1 Task 11.7, starting on page 317 in the PG.

 

From: Bryan Bartik [mailto:[email protected]] 
Sent: Saturday, July 04, 2009 11:03 AM
To: [email protected]
Cc: [email protected]
Subject: Re: [OSL | CCIE_RS] workbook 1 lab 9 - cat addressing

 

Eric, what volume is this? What page of the PG are you looking at? 

Thanks,

On Sat, Jul 4, 2009 at 9:51 AM, Eric Stanfield <[email protected]>
wrote:

Apologies if I am again missing something written in the guide, but I can't
seem to find any indication of what interfaces should be built on the 4
switches in order to peer them together in as10101.  When I load the configs
into the proctorlabs rack, cat1 has a svi in 150.100.81.0/24 with which it
can later peer with R8 and then a handful of routed interfaces which appear
to be one side of routed links to the other three cats.  Cat2 has no l3
interfaces until the 200.x.x.x loopbacks are created.  Cat3 and Cat4 have no
l3 interfaces at all.

The PG shows Cat2/3/4 being configured with network commands referencing the
subnets shown in the bottom right of diagram 1.  Is this some unspoken task
of having to finalize the routed link configs on Cat2/3/4 or am I just
missing something obvious.

Thanks




-- 
Bryan Bartik
CCIE #23707 (R&S), CCNP
Sr. Support Engineer - IPexpert, Inc.
URL: http://www.IPexpert.com

Reply via email to