Rainer Hansen writes:
> thanks for the tip but it does not seem to work. All columns seem to
> be filled with values except of the Estim colum. There are no values
> displayed.
>
> I have done the clocking manually without the help of Org-Mode. The
> values in my case are actually no estimates bu
> On Monday 06 April 2009 19:37:07 Manish wrote:
>> On Mon, Apr 6, 2009 at 6:05 PM, Rainer Hansen wrote:
>> > Hi,
>> >
>> > I am new to Org-Mode and I have written a number of project
tasks in the
>> > following form:
>> >
>> > * Project
>> > ** Task 1
>> > <
Hi Manish,
thanks for the tip but it does not seem to work. All columns seem to be filled
with values except of the Estim colum. There are no values displayed.
I have done the clocking manually without the help of Org-Mode. The values in
my case are actually no estimates but rather the clocked
On Mon, Apr 6, 2009 at 6:05 PM, Rainer Hansen wrote:
> Hi,
>
> I am new to Org-Mode and I have written a number of project tasks in the
> following form:
>
> * Project
> ** Task 1
> <2009-03-19 Thu 13:15-13:35>
> Description of Task 1
> ** Task 2
> <2009-03-18 Wed 12:15-13:35>
> Description of
Hi,
I am new to Org-Mode and I have written a number of project tasks in the
following form:
* Project
** Task 1
<2009-03-19 Thu 13:15-13:35>
Description of Task 1
** Task 2
<2009-03-18 Wed 12:15-13:35>
Description of Task 2
** Task 3
SCHEDULED: <2009-03-11 Wed 19:55-21:45>