Wrencher's,
I am having a good debate with a fellow solar installer regarding an NEC 
requirement to isolate a meter between two disconnecting means adjacent to the 
meter when grid connecting via a tap.   My thought is that if we have a load 
center with breakers to combine multiple inverters on the roof, the PV meter 
can be located in the basement between the roof load center and a fused 
disconnect adjacent to the tap with no need for a disconnect next to the meter 
on the load center side of the meter.  Can anyone reference a section in the 
code that requires a disconnecting means adjacent to both sides of the meter?  
The meter I am referencing simply records the total kWh's of the solar system 
as required by the State incentive program.

All feedback is appreciated.
Al Frishman
AeonSolar

(917) 699-6641 - cell
(888) 460-2867
www.aeonsolar.com


_______________________________________________
List sponsored by Home Power magazine

List Address: RE-wrenches@lists.re-wrenches.org

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to