Hello, We have our first grid-tied install involving a propane generator coming up soon. No batteries. Customer will be getting a panel upgrade with the system.
Specifically: 1.When sizing the replacement panel, do I have to account for the main, gen, and pv? 2.Will the pv sense the generator output as grid voltage and sync/output? 3.If so: during a power outage and while gen is operating, what if pv production is higher than the house loads? Thanks for the input! Eric Sent from my Verizon Wireless BlackBerry _______________________________________________ List sponsored by Home Power magazine List Address: RE-wrenches@lists.re-wrenches.org Options & settings: http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org List rules & etiquette: www.re-wrenches.org/etiquette.htm Check out participant bios: www.members.re-wrenches.org