Friends:

I was not aware that the goal was to install the point of connection ahead of the meter. The section says: "A photovoltaic power source shall be permitted to be connected to the supply side of the service disconnecting means..."(emphasis added). The goal is to be down stream of the utility meter. Otherwise you are giving away your PV generated electricity.

Granted this is not always easy, but most switch gear has provisions for a fire pump and this is the point where you connect.

William Miller


At 07:00 PM 3/10/2009, you wrote:
I hope I can help. If he installs ahead of the meter (line side install) he is installing a new service.
_______________________________________________
List sponsored by Home Power magazine

List Address: RE-wrenches@lists.re-wrenches.org

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to