At 06:24 PM 11/19/2008, you wrote:
Is there any issue connecting a batteryless grid-tie PV system to
the load side of a panel that is backed-up by a generator on an
automatic transfer switch, when the grid is down and the generator running?
It is recommended to use a relay to disconnect the inverter when the
panel is being fed by the generator.