+1

Regards,
Mark

Mark Beierl
SW System Sr Principal Engineer
Dell EMC | Office of the CTO
mobile +1 613 314 8106<tel:1-613-314-8106>
[email protected]<mailto:[email protected]>

On Oct 4, 2017, at 14:44, David McBride 
<[email protected]<mailto:[email protected]>> wrote:

Team,

Please respond to this mail with (+1, 0, -1) and your thoughts, suggestions, or 
alternatives.

During the TSC call on Tues, Oct 3, the TSC agreed to slip the initial 
Euphrates release (5.0) to October 20.  In addition, I also proposed 
eliminating one of the two point releases (5.1, 5.2) planned for Euphrates.  
The reasoning was as follows:

  1.  Moving the 5.0 release to Oct 20 places that release just 3 weeks before 
the planned release of 5.1 (Nov 10).
  2.  Slipping 5.1 and 5.2 could have negative consequences for the OPNFV "F" 
release, as happened with Euphrates when we decided to slip Danube 3.0.

Therefore, the proposal is to eliminate the planned release on Nov 10, so that 
there would just be one point release on Dec 15.

The proposal is described in more detail in the slide deck that I presented 
during the TSC 
meeting<https://wiki.opnfv.org/display/meetings/TSC#TSC-October3,2017> (see 
link labeled "euphrates contingency.pptx" under the heading "Euphrates update").

David

--
David McBride
Release Manager, OPNFV
Mobile: +1.805.276.8018<tel:%2B1.805.276.8018>
Email/Google Talk: 
[email protected]<mailto:[email protected]>
Skype: davidjmcbride1
IRC: dmcbride
_______________________________________________
opnfv-project-leads mailing list
[email protected]<mailto:[email protected]>
https://lists.opnfv.org/mailman/listinfo/opnfv-project-leads

_______________________________________________
opnfv-tech-discuss mailing list
[email protected]
https://lists.opnfv.org/mailman/listinfo/opnfv-tech-discuss

Reply via email to