Team,

Please respond to this mail with (+1, 0, -1) and your thoughts,
suggestions, or alternatives.

During the TSC call on Tues, Oct 3, the TSC agreed to slip the initial
Euphrates release (5.0) to October 20.  In addition, I also proposed
eliminating one of the two point releases (5.1, 5.2) planned for
Euphrates.  The reasoning was as follows:

   1. Moving the 5.0 release to Oct 20 places that release just 3 weeks
   before the planned release of 5.1 (Nov 10).
   2. Slipping 5.1 and 5.2 could have negative consequences for the OPNFV
   "F" release, as happened with Euphrates when we decided to slip Danube 3.0.

Therefore, the proposal is to eliminate the planned release on Nov 10, so
that there would just be one point release on Dec 15.

The proposal is described in more detail in the slide deck that I presented
during the TSC meeting
<https://wiki.opnfv.org/display/meetings/TSC#TSC-October3,2017> (see link
labeled "euphrates contingency.pptx" under the heading "Euphrates update").

David

-- 
*David McBride*
Release Manager, OPNFV
Mobile: +1.805.276.8018
Email/Google Talk: [email protected]
Skype: davidjmcbride1
IRC: dmcbride
_______________________________________________
opnfv-tech-discuss mailing list
[email protected]
https://lists.opnfv.org/mailman/listinfo/opnfv-tech-discuss

Reply via email to