On 12/03/2010 03:21 PM, Matthew Petach wrote: > On Thu, Dec 2, 2010 at 8:58 PM, Alex Rubenstein <a...@corp.nac.net> wrote: > ... >> Anyway, back to topic: Vendors, please a) get all your gear to cool >> front-to-back, and b) let it take 480 polyphase and not require a neutral. >> I, for one, will be happier. The datacenter of tomorrow (hell, today) >> require this. >> > > People are still feeding their gear with AC? Save on PS inefficiency, > and feed direct 12/5vDC to the servers. Save space, save power, > save cooling.
If you're already in a datacenter, getting 208V AC from an existing AC infrastructure is a lot easier, cheaper, and sometimes more plausible than building a DC plant. If you have your own facility, it's a different story, but if you do colo, you probably have more customers expecting AC than DC, so you'll at least need to maintain both infrastructure. -- Kevin Stange Chief Technology Officer Steadfast Networks http://steadfast.net Phone: 312-602-2689 ext. 203 | Fax: 312-602-2688 | Cell: 312-320-5867
signature.asc
Description: OpenPGP digital signature