Nicolas Goaziou <m...@nicolasgoaziou.fr> writes: > Hello, > > Malcolm Matalka <mmata...@gmail.com> writes: > >> I'm on 8.2.10 and want to upgrade to the latest version in ELPA for est+ >> views, but I noticed that summation with {:} in column view does not >> give output in days. I've poked around the code a bit and it doesn't >> seem to me like a configuration change. >> >> Is there any way to get effort estimates printed in days (where number >> of days is based on org-effort-durations? >> >> The motivation for this is I'm planning a large project where the summed >> estimates are in days and 180 hours is more difficult to grasp than 22.5 >> days. > > You can control the output with `org-time-clocksum-format' (which should > be named differently BTW). See also `org-time-clocksum-use-fractional' > and `org-time-clocksum-fractional-format'.
>From what I can tell, those apply to CLOCKSUM but in this case I'm using {:} for effort. Do they still apply there? I can see that CLOCKSUM already uses days in the format but I'm not seeing it on the output for Effort sums. Am I misunderstanding your response? > > Regards,