Hello,

Malcolm Matalka <mmata...@gmail.com> writes:

> I'm on 8.2.10 and want to upgrade to the latest version in ELPA for est+
> views, but I noticed that summation with {:} in column view does not
> give output in days.  I've poked around the code a bit and it doesn't
> seem to me like a configuration change.
>
> Is there any way to get effort estimates printed in days (where number
> of days is based on org-effort-durations?
>
> The motivation for this is I'm planning a large project where the summed
> estimates are in days and 180 hours is more difficult to grasp than 22.5
> days.

You can control the output with `org-time-clocksum-format' (which should
be named differently BTW). See also `org-time-clocksum-use-fractional'
and `org-time-clocksum-fractional-format'.

Regards,

-- 
Nicolas Goaziou