Hello, Malcolm Matalka <mmata...@gmail.com> writes:
> I'm on 8.2.10 and want to upgrade to the latest version in ELPA for est+ > views, but I noticed that summation with {:} in column view does not > give output in days. I've poked around the code a bit and it doesn't > seem to me like a configuration change. > > Is there any way to get effort estimates printed in days (where number > of days is based on org-effort-durations? > > The motivation for this is I'm planning a large project where the summed > estimates are in days and 180 hours is more difficult to grasp than 22.5 > days. You can control the output with `org-time-clocksum-format' (which should be named differently BTW). See also `org-time-clocksum-use-fractional' and `org-time-clocksum-fractional-format'. Regards, -- Nicolas Goaziou