I have reviewed the issues that we have so far for AOO 4.1.1, the
translation deadline and updates we have, the testing activities etc.
and I propose the following schedule for our upcoming AOO 4.1.1 bugfix
release.
July 8th, milestone build m2
July 18th, translation deadline
July 23th, milestone build m3
August 1th, RC1
- depending on feedback etc. further RC candidates on demand
August 26th GA (or earlier, depending on feedback and QA outcome)
One of the biggest problems is the upload speed and I calculate at the
moment with ~3 days. It's still a pain and no fun.
Any opinions or comments?
Looking at the current list of issues requested to be considered for
planned 4.1.1 release - the so-called release-blockers - the proposed
schedule makes sense to me.
Having a look on the bucket of issues submitted since our 4.1.0 release
which are not solved and not completely reviewed until now I could
imagine that the are some more issues which we might consider for our
planned 4.1.1 release. If this is the case we should live with a 1-2
week shift of the proposed schedule.