Hi, I have reviewed the issues that we have so far for AOO 4.1.1, the translation deadline and updates we have, the testing activities etc. and I propose the following schedule for our upcoming AOO 4.1.1 bugfix release.
July 8th, milestone build m2 July 18th, translation deadline July 23th, milestone build m3 August 1th, RC1 - depending on feedback etc. further RC candidates on demand August 26th GA (or earlier, depending on feedback and QA outcome) One of the biggest problems is the upload speed and I calculate at the moment with ~3 days. It's still a pain and no fun. Any opinions or comments? Juergen --------------------------------------------------------------------- To unsubscribe, e-mail: dev-unsubscr...@openoffice.apache.org For additional commands, e-mail: dev-h...@openoffice.apache.org