and I propose the following schedule for our upcoming AOO 4.1.1 bugfix
release.

July 8th, milestone build m2
July 18th, translation deadline
July 23th, milestone build m3
August 1th, RC1
- depending on feedback etc. further RC candidates on demand
August 26th GA (or earlier, depending on feedback and QA outcome)

One of the biggest problems is the upload speed and I calculate at the
moment with ~3 days. It's still a pain and no fun.