Per FLIP-145, we have many runtime operators to implement and bridge it with 
the planner.

Best,
Danny Chan
在 2020年10月19日 +0800 PM6:59,Robert Metzger <rmetz...@apache.org>,写道:
> Thank you for your responses so far.
>
> @Kurt, Jingsong, Danny: Which JIRAs/FLIPs are going to benefit from the
> extension?
>
> On Mon, Oct 19, 2020 at 12:45 PM Aljoscha Krettek <aljos...@apache.org>
> wrote:
>
> > @Robert Your (and Dian's) suggestions sound good to me! I like keeping
> > to master frozen for a while since it will prevent a lot of duplicate
> > merging efforts.
> >
> > Regarding the date: I'm fine with the proposed date but I can also see
> > that extending it to the end of the week could be helpful.
> >
> > Aljoscha
> >
> > On 19.10.20 12:24, Danny Chan wrote:
> > > +1 for Kurt suggestion, there are many features for SQL yet, 2 more days
> > are valuable.
> > >
> > > Best,
> > > Danny Chan
> > > 在 2020年10月19日 +0800 PM6:22,Jingsong Li <jingsongl...@gmail.com>,写道:
> > > > Hi Robert,
> > > >
> > > > Thanks for your detailed explanation.
> > > >
> > > > At present, we are preparing or participating in Flink forward, so +1
> > for
> > > > appropriate extension of deadline.
> > > >
> > > > Best,
> > > > Jingsong
> > > >
> > > > On Mon, Oct 19, 2020 at 5:36 PM Kurt Young <ykt...@gmail.com> wrote:
> > > >
> > > > > Can we change the freeze date to October 30th (Friday next week)? It
> > would
> > > > > be helpful
> > > > > for us if we have 2 more days.
> > > > >
> > > > > Best,
> > > > > Kurt
> > > > >
> > > > >
> > > > > On Mon, Oct 19, 2020 at 5:00 PM Robert Metzger <rmetz...@apache.org>
> > > > > wrote:
> > > > >
> > > > > > Hi all,
> > > > > >
> > > > > > Dian and I would like to discuss a few items regarding the upcoming
> > Flink
> > > > > > 1.12 feature freeze:
> > > > > >
> > > > > > *A) Exact feature freeze day*
> > > > > > So far, we've always said "end of October
> > > > > > <https://cwiki.apache.org/confluence/display/FLINK/1.12+Release>" 
> > > > > > for
> > > > > the
> > > > > > freeze. We propose (end of day CEST) October 28th (Wednesday next
> > week)
> > > > > as
> > > > > > the feature freeze time.
> > > > > > We want to create RC0 on the day after the feature freeze, to make
> > sure
> > > > > the
> > > > > > RC creation process is running smoothly, and to have a common 
> > > > > > testing
> > > > > > reference point.
> > > > > >
> > > > > >
> > > > > >
> > > > > > *B) What does feature freeze mean?*After the feature freeze, no new
> > > > > > features are allowed to be merged to master. Only bug fixes and
> > > > > > documentation improvements.
> > > > > > The release managers will revert new feature commits after the 
> > > > > > feature
> > > > > > freeze.
> > > > > > Rational: The goal of the feature freeze phase is to improve the
> > system
> > > > > > stability by addressing known bugs. New features tend to introduce 
> > > > > > new
> > > > > > instabilities, which would prolong the release process.
> > > > > > If you need to merge a new feature after the freeze, please open a
> > > > > > discussion on the dev@ list. If there are no objections by a PMC
> > member
> > > > > > within 48 (workday)hours, the feature can be merged.
> > > > > >
> > > > > > *C) When to cut the "release-1.12" branch off master?*
> > > > > > In the last feature freeze, we had a pretty lengthy phase of
> > maintaining
> > > > > > the "master" and "release-1.11" branches with the same fixes.
> > Therefore,
> > > > > I
> > > > > > would like to propose an adjustment to the release process: We will
> > have
> > > > > a
> > > > > > stabilization phase on master, between the feature freeze and the
> > branch
> > > > > > cut.
> > > > > > I expect this stabilization phase to last between 1 and 3 weeks,
> > > > > depending
> > > > > > on the issues we find. Once all blockers are resolved, and no new
> > > > > blockers
> > > > > > are surfacing, we can cut off the "release-1.12" branch and finalize
> > the
> > > > > > release.
> > > > > > Is anybody in the community waiting for the cut off to happen sooner
> > so
> > > > > > that they can merge a big feature to Flink 1.13 ? (if that would be
> > the
> > > > > > case, then we can not have a stabilization phase)
> > > > > >
> > > > > >
> > > > > > Let me know what you think!
> > > > > >
> > > > > > Best,
> > > > > > Dian and Robert
> > > > > >
> > > > >
> > > >
> > > >
> > > > --
> > > > Best, Jingsong Lee
> > >
> >
> >