I will start a separate discussion on 4 month cycle or longer, but wanted to 
call out one more important date.

We have a last day for feature proposal date which is typically a month before 
feature freeze date. If following 4.3 schedule + 4 month it would have been 
2/14 and we are already past that. Since it was not announced for 4.4 release 
yet my suggestion would be to keep feature proposal open for another week and 
push all  the dates out by 2 weeks to give folks opportunity to finish up their 
features for new proposals that are yet to come out.

To be clear that would mean pushing out feature freeze to 3/28 from 3/14 and 
all the other dates likewise. 


Thanks
Animesh

> -----Original Message-----
> From: Animesh Chaturvedi [mailto:animesh.chaturv...@citrix.com]
> Sent: Tuesday, February 25, 2014 1:05 PM
> To: dev@cloudstack.apache.org
> Subject: RE: 4.4 Feature Freeze
> 
> With the experience of 4.2 and 4.3 I think we should discuss if we can
> realistically achieve 4 month cycle our RCs take 2 months. I was going to
> open up the discussion after 4.3 is shipped though.
> 
> > -----Original Message-----
> > From: Trippie [mailto:trip...@gmail.com] On Behalf Of Hugo Trippaers
> > Sent: Tuesday, February 25, 2014 8:50 AM
> > To: <dev@cloudstack.apache.org>
> > Subject: Re: 4.4 Feature Freeze
> >
> > Hey,
> >
> > If we stick to our 4 month release schedule the feature freeze is four
> > months after the feature freeze of 4.3. The feature freeze of 4.3 was 8 Nov
> 2013.
> >
> > So the proposed release schedule for 4.4 would look like this (dates
> > slightly modified to take efficiency and RM's personal life into account 
> > ;-) ):
> >
> > Feature Freeze:                     March 14, 2014
> > Testing/Bug Fixes:                  March 15, 2014 till April 18, 2014
> > (direct access for committers)
> > Stability Fixes only:                       April 19, 2014 till release 
> > (cherry picks
> > by RM only)
> > First RC:                                   May 9, 2014
> > Optimistic Release Date:    May 19, 2014
> >
> > Cheers,
> >
> > Hugo
> >
> >
> > On 25 feb. 2014, at 16:35, Sudha Ponnaganti
> > <sudha.ponnaga...@citrix.com>
> > wrote:
> >
> > > Hi,
> > >
> > > I am also looking for feature freeze dates for 4.4. Can RM post those?
> > >
> > > Thanks
> > > /Sudha
> > >
> > > -----Original Message-----
> > > From: Alex Hitchins [mailto:alex.hitch...@shapeblue.com]
> > > Sent: Tuesday, February 25, 2014 7:00 AM
> > > To: dev@cloudstack.apache.org
> > > Subject: 4.4 Feature Freeze
> > >
> > > All,
> > >
> > > I know the 4.3 isn't quite out the door yet, but is there a
> > > timetable
> > somewhere stating when the feature freeze for 4.4 will be?
> > >
> > > I would like to submit a feature and want to ensure that It's
> > > prepared in
> > time.
> > >
> > > Many thanks,
> > >
> > > Alex
> > >
> > >
> > > Regards,
> > >
> > > Alex Hitchins
> > > VP Software Engineering
> > > D: +44 1892 523 587 | S: +44 20 3603 0540<tel:+442036030540> | M:
> > +44<tel:+447968161581> 7788 423 969
> > >
> > > ShapeBlue Ltd, 53 Chandos Place, Covent Garden, London, WC2N 4HS
> > >
> > > Need Enterprise Grade Support for Apache CloudStack?
> > > Our CloudStack Infrastructure
> > > Support<http://shapeblue.com/cloudstack-
> > infrastructure-support/> offers the best 24/7 SLA for CloudStack
> > Environments.
> > >
> > > Apache CloudStack Bootcamp training courses
> > >
> > > **NEW!** CloudStack 4.2.1 training<http://shapeblue.com/cloudstack-
> > training/>
> > > 18th-19th February 2014, Brazil.
> > Classroom<http://shapeblue.com/cloudstack-training/>
> > > 17th-23rd March 2014, Region A. Instructor led, On-
> > line<http://shapeblue.com/cloudstack-training/>
> > > 24th-28th March 2014, Region B. Instructor led, On-
> > line<http://shapeblue.com/cloudstack-training/>
> > > 16th-20th June 2014, Region A. Instructor led, On-
> > line<http://shapeblue.com/cloudstack-training/>
> > > 23rd-27th June 2014, Region B. Instructor led, On-
> > line<http://shapeblue.com/cloudstack-training/>
> > >
> > > This email and any attachments to it may be confidential and are
> > > intended
> > solely for the use of the individual to whom it is addressed. Any
> > views or opinions expressed are solely those of the author and do not
> > necessarily represent those of Shape Blue Ltd or related companies. If
> > you are not the intended recipient of this email, you must neither
> > take any action based upon its contents, nor copy or show it to
> > anyone. Please contact the sender if you believe you have received
> > this email in error. Shape Blue Ltd is a company incorporated in
> > England & Wales. ShapeBlue Services India LLP is a company
> > incorporated in India and is operated under license from Shape Blue
> > Ltd. Shape Blue Brasil Consultoria Ltda is a company incorporated in
> > Brasil and is operated under license from Shape Blue Ltd. ShapeBlue is a
> registered trademark.

Reply via email to