On Fri, Jul 22, 2022 at 1:08 PM Jacob Wujciak <ja...@voltrondata.com.invalid> wrote: > > Hello Everyone, > > Currently there have been 452 JIRA tickets resolved for 9.0.0 with 23 > tickets (ex. blockers) still open, good job everyone! > > Thanks to everyone's work we were able to reduce the number of blockers and > have PRs [1][2][3] for 3/5 open blockers that mostly require reviews. The > following two C++ issues have seen little activity recently will require > some attention prior to the release: > - ARROW-16692 StackOverflow in merge generator [4] No activity since June, > it looks like the actual solution is dependent on other issues but an error > message to prevent a hard crash could be a workaround for now. > - ARROW-15678 A complex issue with compiler optimization and homebrew. [5] > > Regardless of the status of these blockers we will create the release > branch on monday to initiate the "feature freeze" after that only fixes for > the blockers (or issues that pop up during verification) will be cherry > picked from master.At this point all open, non-blocker issues will be moved > to 10.0.0. Development on master can of course continue as usual but if you > are able, please try to help with the blockers.
Just created the maint-9.0.0 branch according to the original schedule. We still have 10 bugs left from the release [1], I can start creating the first release candidate as soon as they get resolved. Thanks, Krisztian [1]: https://issues.apache.org/jira/projects/ARROW/versions/12351550 > > Thanks! > > [1]: https://issues.apache.org/jira/browse/ARROW-16700 > [2]: https://issues.apache.org/jira/browse/ARROW-17115 > [3]: https://issues.apache.org/jira/browse/ARROW-16887 > [4]: https://issues.apache.org/jira/browse/ARROW-16692 > [5]: https://issues.apache.org/jira/browse/ARROW-15678 > > > > On Mon, Jul 18, 2022 at 12:08 PM Raul Cumplido Dominguez > <r...@voltrondata.com.invalid> wrote: > > > Hi, > > > > We are still targeting next Monday 25th of July to start creating the first > > release candidate for 9.0.0. > > > > We are down to 37 Open/In progress issues and 6 blockers from 144 issues > > and 7 blockers from a couple of weeks ago. Thanks everyone for the great > > effort there! > > > > This is the link to the confluence page that was made to track the progress > > for the 9.0.0 release [1]. > > > > As usual when approaching a release we have started seeing an increased > > number of failed nightly builds, it would be great if you could take a look > > for possible issues introduced by your changes [2] [3]. > > > > We have started tagging the tasks related to the nightlies with a Nightly > > label so it's easier to query them [4]. > > > > There have been 447 Resolved/Closed JIRA tickets so far! Lots of good > > things on the new release! > > > > Thank you, > > Raúl > > > > [1] https://cwiki.apache.org/confluence/display/ARROW/Arrow+9.0.0+Release > > [2] > > https://ursalabs.zulipchat.com/#narrow/stream/181017-nightlies/topic/report > > [3] https://crossbow.voltrondata.com/ > > [4] > > > > https://issues.apache.org/jira/issues/?jql=labels%20%3D%20Nightly%20and%20status%20not%20in%20(Resolved%2C%20Closed) > > > > > > > > > > On Tue, Jul 5, 2022 at 5:01 PM Raul Cumplido Dominguez < > > r...@voltrondata.com> > > wrote: > > > > > Hi, > > > > > > An update around the next release. > > > > > > The plan is to start preparing the 9.0.0 release around the 25th of July, > > > which means we probably will be cutting a release in ~3 weeks from now. > > > > > > This is the link to the confluence page that was made to track the > > > progress for the 9.0.0 release [1]. > > > > > > There are currently 7 blockers identified and 144 issues Open/In progress > > > with a target release 9.0.0. > > > > > > It would be great for the process of preparing the release if you could > > > review tickets that are assigned to you in the "TODO Backlog" and move > > > those tickets that you think you will not be able to close to "Version > > > 10.0.0" in JIRA, so that we can start preparing release announcements etc > > > with a good estimate of what's actually going to end up in the release. > > > > > > I will start moving some of the Unassigned tickets to the 10.0.0. > > > > > > Thank you, > > > Raúl > > > > > > [1] > > https://cwiki.apache.org/confluence/display/ARROW/Arrow+9.0.0+Release > > > > > > On Wed, Jun 22, 2022 at 4:42 PM Raul Cumplido Dominguez < > > > r...@voltrondata.com> wrote: > > > > > >> Hi, > > >> > > >> I am sending this email a little earlier than usual to bring awareness > > >> for the upcoming release. > > >> The plan seems to be to start preparing the 9.0.0 release around mid > > >> July, which means we probably will be cutting a release in ~3.5 / ~4 > > weeks > > >> from now. > > >> A confluence page was made to track the progress for the 9.0.0 release > > >> [1]. > > >> > > >> It would be great for the process of preparing the release if you could > > >> review tickets that are assigned to you in the "TODO Backlog" and move > > >> those tickets that you think you will not be able to close to "Version > > >> 10.0.0" in JIRA, so that we can start preparing release announcements > > etc > > >> with a good estimate of what's actually going to end up in the release. > > >> > > >> Thanks everybody for the great work! So far almost 300 tickets seem to > > >> have been resolved as part of 9.0.0! > > >> > > >> Thank you, > > >> Raúl > > >> > > >> [1] > > https://cwiki.apache.org/confluence/display/ARROW/Arrow+9.0.0+Release > > >> > > > > >