On 12/06/2011 08:44 AM, Saul Wold wrote:
Attendees:
Beth, Darren, Tom, Matthew, Scott R., Sean, Richard, Paul, Jeff, Denys,
Bruce, Mark, Dave, Song
New Action Item List:
* Action item Review - 5 min
1. Mark will review unsorted features from Wind River team and try to
have them scheduled (WIP)
Focus of the current week:
M1 development and bug fixing, keep features on schedule, get patches
reviewed or pre-reviewed as soon as possible.
Agenda:
* Opens collection - 5 min (Song)
* Opens - 10 min
- Tested Distro - Paul requested that people review the Tested Distro
list and send updates.
Sorry folks, I did not edit this section below correctly, hit the send
button too quickly.
* Yocto 1.0.2 and 1.1.1 point release update - 10 min (Josh/Beth)
1.0.2 is on QA now, there was a problem with the x86-64 build the
OpenSuSE 11.4 Autobuilder machines, we tracked it down to an
LD_LIBRARY_PATH issue inside of binutils. Briefly, binutils builds a
host binary which seems to pick up some target based libraries (since on
an x86-64 host the target x86-64 libraries match), we are still
investigating why this only occurs on OpenSuSE 11.4, so this will be
release note item.
* Yocto 1.2 M1 Status (features development) - 10 min (Song/Beth)
https://wiki.yoctoproject.org/wiki/Yocto_Project_v1.2_Status . We are in
the 5th week of M1. Feature complete coming this weekend
Saul Completely forget to use the Status page, partly because it was not
updated since last week!
A couple of notes
* The build is stable and almost green, issues are identified and
being worked
* P1 Features (Package History & Initial Self-Hosted Minimal Build)
are in, Some P2 work is in also.
* We had 46 packages updated, which should allow us to reach the 50%
goal for M1
* Action item Review - 5 min
1. Mark will review unsorted features from Wind River team and try to
have them scheduled (WIP)
* Weekly team sharing (20 min)
Dave: Manager and
Mark: Internal WR stuff, Bitbake runtask work - mechanism to call into
bitbake, prelinker maybe ARM-eabi prevents linkage
Bruce: Traveling, M2 dev on schedule dev kernel 3.2rc4, Tracking Stable
3.0rt, Main RT at 3.2, kernel updating and BSP refreshes 1.2 will be at
least 3.2
Denys: Nothing
Jeff: Nothing
Paul: Finished BuildHistory - enable on AB?, QT 4.8.0 release, bugfixing
no blockers
Richard: Patch pulling, slowed down by HW issue, moving forward to
address M1 and master updating.
Sean: Nothing
Scott R: Cleaning up Doc Bugs 1773, 1500, continuing with bugs and
working on Website doc pages, no blockers
Matthew: Nothing
Tom: Finished off M1 Intel video acceleration, internal bsp and support
Darren: EFI Support (pounding head on desk), looking into other odd
behavior, internal BSP work.
Beth: License M1 task - custom license, license manifest, license
cleanup, License Audit (team effort in the future), Gearing up for M1
Saul: Recovering from Sick, Pull wrangling, helping Joshua out with
1.0.2 debugging, selfhosted image work
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto