Construction Coordination Question How does the construction industry in your market coordinate the following items. 1. Fire Marshall (AHJ) will only approve 100%, no partial submittals for review and will issue fines if working on a project without a permit. 2. Project requires BIM coordination. 3. Prime Contract accelerates schedule, starting construction as BIM coordination is completed in an area, not as a whole. 4. If the fire sprinkler contractor begins installation with the accelerated schedule, they face fines along with potential field modifications pending Fire Marshall approval. If the fire sprinkler contractor awaits the completion of the BIM coordination to provide 100% submittals for permit, the project progresses without them, impacting installation conditions and additional labor cost.
What say you? Sincerely; Jackie "JW" Ward; SET 1-405-240-7076 [email protected]<mailto:[email protected]> NICET IV Cert. No. 104187 Victaulic Vortex Integrator Firetrol Protection Systems 108 NW 132nd Street; Oklahoma City, OK 73114 405-752-2330 Ext. 10230 Fax:405-752-2297 License No: AR-FSS-162, LA-F415, OK-863 & 302, TX - ECR-1751432, ACR-1751168, SCR-G-0292 [A close-up of a spray object Description automatically generated][A machine on a stand Description automatically generated][cid:[email protected]][Firetrol Oklahoma City BACK] [cid:[email protected]] [Mr_ Jackie _JW_ Ward] https://www.minimax-mxone.com/ Victaulic Vortex<https://www.victaulic.com/vtc_product_categories/victaulic-vortex/>
_________________________________________________________ SprinklerForum mailing list: https://lists.firesprinkler.org/list/sprinklerforum.lists.firesprinkler.org To unsubscribe send an email to [email protected]