No both triggers are independent, so will trigger every two days AND when
the upstream project finishes.
I don't think there is any way at the moment of doing the other case, which
is trigger the project at a certain point only if the upstream project has
run since the previous one.
I think th
Thanks for your reply.
So, when i combine the two condiions (time and trigger), both have to be
true in order that the job will run.
Thanks
David
On Thursday, August 23, 2012 1:27:33 PM UTC+3, cjo wrote:
>
> You can set multiple triggers on a project,
>
> So just set both the "Build after other
You can set multiple triggers on a project,
So just set both the "Build after other projects are built" and the "Build
periodically" on the project.
Chris,
On Thursday, August 23, 2012 10:02:46 AM UTC+1, David Gang wrote:
>
> Hi all,
>
> I have a job which i want to run on 2 specific days in
Hi all,
I have a job which i want to run on 2 specific days in a week.
On the other hand it has to be run after another job is run (which is
run every day).
I want somehow to combine the periodic build with the option to run
this project just after the other project was run at the same day.
How d