Thanks for your reply. So, when i combine the two condiions (time and trigger), both have to be true in order that the job will run.
Thanks David On Thursday, August 23, 2012 1:27:33 PM UTC+3, cjo wrote: > > You can set multiple triggers on a project, > > So just set both the "Build after other projects are built" and the "Build > periodically" on the project. > > Chris, > > On Thursday, August 23, 2012 10:02:46 AM UTC+1, David Gang wrote: >> >> Hi all, >> >> I have a job which i want to run on 2 specific days in a week. >> On the other hand it has to be run after another job is run (which is >> run every day). >> I want somehow to combine the periodic build with the option to run >> this project just after the other project was run at the same day. >> >> How do i achieve this? >> >> Thanks, >> David >> >