PGE:  After you export more than the baseline rate, you start getting
credited at the over-baseline rate.

When there were multiple tiers, you got credited for whatever tier the
production was in.
i.e. baseline rate for the kWh's up to baseline amount, tier 1 rate for
next kWh's up to tier 1 limit, etc.

At one time there were 5 tiers, then 4, then 3, now 2.


Antony Tersol
_______________________________________________
List sponsored by Redwood Alliance

Pay optional member dues here: http://re-wrenches.org

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

There are two list archives for searching. When one doesn't work, try the other:
https://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/
http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
http://www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
http://www.members.re-wrenches.org

Reply via email to