People might also look at Victron inverters.

Jay
Peltz Power. 

> On Feb 23, 2020, at 3:23 AM, Jeff Clearwater <je...@villagepowerdesign.com> 
> wrote:
> 
>  The Sol-Ark manual indicates 240 Volt stacking to 8 units (9 units for 
> 208V).  They list the "12KW" off-grid output as 8 KWs each.  So 64 KWs.
> 
> anybody stacked a signficant number of them yet?
> 
> Looking forward to hearing feedback from experienced installers.
> 
> Best,
> 
> Jeff
> 
> 
> Allan Sindelar wrote on 2/22/20 6:56 PM:
> 
>> 
>> Jeff, according to Midnite’s website, their B-17 inverter can be up to 40 kW 
>> in 2 kW increments. 
>>  Allan
>> 
>>> On Feb 22, 2020, at 8:05 PM, Jeff Clearwater <je...@villagepowerdesign.com> 
>>> wrote:
>>> 
>>>  Ahh you're right all our 120/240 volt systems are less than 24 KW.  I was 
>>> thinking of 230 V 50hz systems with multi-cluster boxes.
>>> 
>>> How large can the Sol-Ark be stacked to?  Anyone with large Sol-Ark system 
>>> experience?
>>> 
>>> I hear Mornignstar and MidNite are working on surge capable off-grid 
>>> inverters.  Anyone have a insight as to their KW goals?
>>> 
>>> Best,
>>> 
>>> Jeff
>>> 
>>> wes kennedy wrote on 2/21/20 1:37 PM:
>>> 
>>>> Hi Jeff,
>>>> 
>>>> I think the biggest split phase sunny island system is 4 units, so that's 
>>>> 24KW. 
>>>> 
>>>> What do you do for larger systems? Segment the loads? Not always very 
>>>> practical. 
>>>> 
>>>> This latest opportunity is for an agricultural building that peaks at 
>>>> 75KW. 
>>>> 
>>>> 
>>>> 
>>>> -Wes Kennedy 303-653-3073
>>>> 
>>>> 
>>>> On Friday, February 21, 2020, 12:47:39 PM MST, Jeff Clearwater 
>>>> <je...@villagepowerdesign.com> wrote:
>>>> 
>>>> 
>>>> All of my SMA Sunny Island Sunny Boy AC coupled systems greater than 12 KW 
>>>> have worked flawlessly and delivered reliable power and good monitoring 
>>>> for years.  Less excited about my Schneider and Outback systems due to 
>>>> callbacks and hassles.  a bit more expensive but worth it IMHO.
>>>> 
>>>> Hope that helps!
>>>> 
>>>> Jeff
>>>> 
>>>> wes kennedy wrote on 2/21/20 9:41 AM:
>>>> Hi friends,
>>>> 
>>>> I keep running across opportunities with 50KW-300KW peak load 
>>>> requirements, on split phase services. Big homes, agriculture etc. 
>>>> 
>>>> Outback, Schneider, SMA can all gang/stack into the 30-50KW range, but 
>>>> north of there, I am not finding many (any?) options? 
>>>> 
>>>> Just found Aims Power 50 KW split phase unit with claims of higher power 
>>>> offerings by special order. Even the 50KW unit is $20K, so quite spendy. 
>>>> Any experience with these guys? 
>>>> 50kw - 50,000 WATT DC TO AC PURE SINE POWER INVERTER CHARGER 384 Vdc TO 
>>>> 220/230/240 Vac
>>>> 
>>>> 
>>>> 
>>>> 
>>>> 50kw - 50,000 WATT DC TO AC PURE SINE POWER INVERTER CHARGER 384 Vdc TO ...
>>>> 50kw - 50,000 WATT DC TO AC PURE SINE POWER INVERTER CHARGER 384 Vdc Split 
>>>> Phase 220/230/240
>>>> 
>>>> 
>>>> Thanks for any input! 
>>>> 
>>>> -Wes Kennedy 303-653-3073
>>>> on this list since the 90's
>>>> 
>>>> 
>>>> _______________________________________________
>>>> List sponsored by Redwood Alliance
>>>> 
>>>> List Address: RE-wrenches@lists.re-wrenches.org
>>>> 
>>>> Change listserver email address & settings:
>>>> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>>>> 
>>>> List-Archive: 
>>>> http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html
>>>> 
>>>> List rules & etiquette:
>>>> www.re-wrenches.org/etiquette.htm
>>>> 
>>>> Check out or update participant bios:
>>>> www.members.re-wrenches.org
>>>> 
>>>> 
>>>> -- 
>>>> ~~~~~~~~~~~
>>>> Jeff Clearwater
>>>> Village Power Design
>>>> linkedin 
>>>> www.villagepowerdesign.com
>>>> cell - 413-559-9763
>>>> ~~~~~~~~~~~~~~~~~~~~~~~
>>> 
>>> 
>>> -- 
>>> ~~~~~~~~~~~
>>> Jeff Clearwater
>>> Village Power Design
>>> linkedin 
>>> www.villagepowerdesign.com
>>> cell - 413-559-9763
>>> ~~~~~~~~~~~~~~~~~~~~~~~
>>> _______________________________________________
>>> List sponsored by Redwood Alliance
>>> 
>>> List Address: RE-wrenches@lists.re-wrenches.org
>>> 
>>> Change listserver email address & settings:
>>> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
>>> 
>>> List-Archive: 
>>> http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html
>>> 
>>> List rules & etiquette:
>>> www.re-wrenches.org/etiquette.htm
>>> 
>>> Check out or update participant bios:
>>> www.members.re-wrenches.org
>>> 
> 
> 
> -- 
> ~~~~~~~~~~~
> Jeff Clearwater
> Village Power Design
> linkedin 
> www.villagepowerdesign.com
> cell - 413-559-9763
> ~~~~~~~~~~~~~~~~~~~~~~~
> _______________________________________________
> List sponsored by Redwood Alliance
> 
> List Address: RE-wrenches@lists.re-wrenches.org
> 
> Change listserver email address & settings:
> http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org
> 
> List-Archive: 
> http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html
> 
> List rules & etiquette:
> www.re-wrenches.org/etiquette.htm
> 
> Check out or update participant bios:
> www.members.re-wrenches.org
> 
_______________________________________________
List sponsored by Redwood Alliance

List Address: RE-wrenches@lists.re-wrenches.org

Change listserver email address & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: 
http://www.mail-archive.com/re-wrenches@lists.re-wrenches.org/maillist.html

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out or update participant bios:
www.members.re-wrenches.org

Reply via email to