Mark:

If it were me, I'd put a disconnect prior to entry to the building. How are you going to service the connections without a disconnecting means?

William Miller


At 03:24 PM 12/18/2009, you wrote:
Hello there,
Due to a lot of concrete and asphalt, we are forced to run our PV source circuits in through one exterior wall, through a crawl space and out through the opposite exterior wall to our inverter and disconnect. We will be using EMT and will not be making any stops while inside the building. We will however need to place a couple of pull-boxes due the various required bends in excess of 360*. Will we be required to place a DC disconnect at the “first readily accessible” point inside the building?

Best regards,

Mark Dickson,
NABCEP Certified Solar PV Installer ™
Oasis Montana Inc.


_______________________________________________
List sponsored by Home Power magazine

List Address: RE-wrenches@lists.re-wrenches.org

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org


No virus found in this incoming message.
Checked by AVG - www.avg.com
Version: 9.0.717 / Virus Database: 270.14.113/2573 - Release Date: 12/17/09 23:35:00

Please note new e-mail address and domain:

William Miller
Miller Solar
Voice :805-438-5600
email: will...@millersolar.com
http://millersolar.com
License No. C-10-773985
_______________________________________________
List sponsored by Home Power magazine

List Address: RE-wrenches@lists.re-wrenches.org

Options & settings:
http://lists.re-wrenches.org/options.cgi/re-wrenches-re-wrenches.org

List-Archive: http://lists.re-wrenches.org/pipermail/re-wrenches-re-wrenches.org

List rules & etiquette:
www.re-wrenches.org/etiquette.htm

Check out participant bios:
www.members.re-wrenches.org

Reply via email to