On Wed, 13 Nov 2019 15:31:58 +0000
Peter Maydell <peter.mayd...@linaro.org> wrote:

> On Wed, 13 Nov 2019 at 15:10, Greg Kurz <gr...@kaod.org> wrote:
> > David is away until the 19th of November, which is the release date
> > of rc2 according to the planning [*]. Then we have rc3 the 26th, and
> > final release (or rc4) the 3rd of December, so it should be ok.
> 
> Please don't actively plan to delay putting changes in
> until later release candidates. The release process
> involves steadily winding up the bar of whether it's
> worth putting in and hopefully reducing the volume
> of changes between rcs. In an ideal world rc3 would
> have very few changes, and then there would be no
> changes at all between rc3 and the final release.
> 

Right. I could discuss with Laurent: David should be back on Monday
actually. Hopefully he can a send a PR before rc2.

> thanks
> -- PMM
> 