On 02/03/2015 13:44, Peter Maydell wrote: > On 2 March 2015 at 21:33, Paolo Bonzini <pbonz...@redhat.com> wrote: >> Looks like there are still a few pull requests pending, and Peter is on >> vacation. Should we really enter hard feature freeze tomorrow? The 2.3 >> planning page in the end never got out the "draft" state. > > Well, I said you probably didn't want to schedule rc0 for > while I was on holiday, but nobody changed the dates... > > My current intention is just to keep applying pullreqs > and then to look again at where we are once I'm back at > work. There are almost certainly pending ARM patches > which I need to assemble into a pullreq too. > >> A possible alternative schedule could be: >> >> 2015-03-10 Tag v2.3.0-rc0 > > Hugely optimistic. I'm not likely to tag rc0 my first day > back at work :-)
I'll take that as a yes for the delay and a no for the schedule... Paolo >> 2015-03-17 Tag v2.3.0-rc1 >> 2015-03-24 Tag v2.3.0-rc2 >> 2015-03-31 Tag v2.3.0-rc3 >> 2015-04-03 Tag v2.3.0 (or -rc4, with release on April 7th) > > -- PMM >