Hi,

On 7 March 2012 10:36, John R Pierce <pie...@hogranch.com> wrote:
> On 03/06/12 3:31 PM, Ondrej Ivanič wrote:
>>
>> - one side completely down: Client should use switch to other side
>> transparently (Failover / High Availability)
>
>
> what happens if the link between the sites is down and both sides decide
> they are master?  then how do you put the pieces back together ?

Good catch! From application point of it is quite easy to sync data
between sites. Let's assume that writes should be disabled in this
scenario.

-- 
Ondrej Ivanic
(ondrej.iva...@gmail.com)

-- 
Sent via pgsql-general mailing list (pgsql-general@postgresql.org)
To make changes to your subscription:
http://www.postgresql.org/mailpref/pgsql-general

Reply via email to