Hello community,

Fresh blood is joining us. New project proposals are coming. I want to take 
this opportunity to give an overview of the process of bringing a project to 
OPNFV.


  1.  History of Process

General Project Lifecycle is documented in [1]. Project promotion, and 
demotion, across states can only be done by TSC review and voting. During the 
reviews, the candidate projects are evaluated based on predefined metrics and 
KPIs. The target numbers may vary for the different levels. In order for 
creation review in TSC, proposals need to be emailed to TSC mailing list, and 
posted for two weeks. Various review criteria are available in [1].

In practice, after OPNFV was founded, we started to discuss new project 
proposals in TSC meeting on 10/21/2014 [1]. TSC spent 2 hours to discuss 
several projects. None could be agreed. TSC realized that a separate community 
discussion was needed to discuss project proposals, help proposals get mature 
before it could go to TSC for creation review. See minutes [1] regarding the 
topic "Recurring weekly calls on general technical content" and the action to 
create a separate weekly meeting on wiki dedicated to discussing project 
proposals.

The first weekly technical discussion started on 10/30/2014, and history 
maintained in [3]. Project proposals were reviewed and discussed on 10/30/2014, 
11/06/2014, 11/13/2014 and 11/20/2014. And the first project was approved by 
TSC on 11/25/2014 after that project got community feedback, made best effort 
to resolve community comments, made several revisions and discussed in those 4 
weekly meetings.

  *   Note: due to wiki upgrade in March 2016, all details of records of agenda 
and minutes of weekly technical discussion [3] before 03/24/2016 were lost.


  1.  Process Overview

Step 1: create your proposal in wiki [4], and email to TSC and Tech-Discussion 
mailing list
Step 2: schedule a community review and discussion in weekly technical 
discussion. The review process is documented in [3].

  *   This community review is the major part of the process, and it may take 
several weeks and iterate several rounds.
  *   2-week review period is the minimum period, i.e. a "necessary condition", 
but NOT a "sufficient condition" to bring to TSC for creation review
  *   A consensus from community review is normally expected to recommend the 
project proposal for TSC creation review.
  *   This process was designed by Founding TSC and its leadership, started 
with the 1st project (reviewed for 4 rounds based on available record), and a 
case study below.
  *   All approved projects have followed this process.
Step 3: once TSC receives the recommendation from community review in weekly 
technical discussion, TSC will schedule a creation review, and vote to approve 
or disapprove this proposal.


  1.  A Case Study

Let us look at a case study based on available details of wiki record [3]. The 
examples are 2 projects proposed in May 2016 - the earliest time that details 
of wiki record are available [3]:

  *   VNF Event Stream
     *   Announced in early May 2016
     *   Discussed in weekly technical discussions on 05/12/2016, 05/19/2016 
and 05/26/2016 (3 rounds).
     *   Founders worked with community, revised proposal based on feedback, 
resolved all comments and get consensus from community for TSC creation review
        *   "The group reached the consensus to recommend it for TSC Creation 
Review." [5]
     *   TSC (2015-2016) did Creation Review on 05/31/2016 and approved it [6].
  *   Daisy
     *   Announced in early May 2016
     *   Discussed in weekly technical discussions on 05/12/2016, 05/19/2016 
and 06/02/2016 (3 rounds).
     *   Founders worked with community, revised proposal based on feedback, 
resolved all comments and get consensus from community for TSC creation review
        *   "The group reached the consensus to recommend Daisy for 
NFV<https://wiki.opnfv.org/display/PROJ/Daisy+Nfv> for TSC Creation Review next 
week" [7]
     *   TSC (2015-2016) did Creation Review on 06/07/2016 [8] and 06/14/2016 
[9] (2 rounds), and eventually approved it on 06/14/2016 [9].


  1.  Essence of Process

The essence of process is to foster community review and fulfill the metric of 
"Proposal has been socialized with potentially interested or affected projects 
and/or parties" [1] in a more realizable and achievable way. This process was 
designed by Founding TSC and its Leadership, started with the initial set of 
project proposals including the 1st approved project in OPNFV. All approved 
projects have followed this process as far as I remember. And the community 
consensus is expected in order to be able to bring to TSC for creation review, 
i.e. "reached consensus to recommend for TSC creation review" or similar 
conclusion at the end of community review in weekly technical discussions. The 
community review may last several rounds as shown in the example of 1st 
approved project and 2 projects in case study. The founder of a project, either 
new or promotion, is expected to work with community, and make the best effort 
and attempt to resolve community comments, such as necessary revision based on 
community feedback, and achieve consensus within community.

Certainly, there is always room for process improvement. So any suggestion is 
welcome to improve the process.

Thank you
Bin

[1] 
https://www.opnfv.org/software/technical-project-governance/project-lifecycle
[2] 
http://meetbot.opnfv.org/meetings/opnfv-meeting/2014/opnfv-meeting.2014-10-21-14.01.html
[3] https://wiki.opnfv.org/display/PROJ/Weekly+Technical+Discussion
[4] https://wiki.opnfv.org/display/PROJ/Project+Proposals
[5] https://wiki.opnfv.org/display/PROJ/tc+minutes+20160526
[6] 
http://meetbot.opnfv.org/meetings/opnfv-meeting/2016/opnfv-meeting.2016-05-31-14.00.html
[7] https://wiki.opnfv.org/display/PROJ/tc+minutes+20160602
[8] 
http://meetbot.opnfv.org/meetings/opnfv-meeting/2016/opnfv-meeting.2016-06-07-13.59.html
[9] 
http://meetbot.opnfv.org/meetings/opnfv-meeting/2016/opnfv-meeting.2016-06-14-13.59.html

-=-=-=-=-=-=-=-=-=-=-=-
Links: You receive all messages sent to this group.

View/Reply Online (#23487): 
https://lists.opnfv.org/g/opnfv-tech-discuss/message/23487
Mute This Topic: https://lists.opnfv.org/mt/33019055/21656
Group Owner: opnfv-tech-discuss+ow...@lists.opnfv.org
Unsubscribe: https://lists.opnfv.org/g/opnfv-tech-discuss/unsub  
[arch...@mail-archive.com]
-=-=-=-=-=-=-=-=-=-=-=-

Reply via email to