We once moved a 3u server 30 miles between data centers this way.  Plug 
redundant psu into a ups and 2 people carried it out and put them in a vehicle. 
 


Sent from my iPhone

> On Sep 1, 2020, at 11:58 PM, Christopher Morrow <morrowc.li...@gmail.com> 
> wrote:
> 
> On Tue, Sep 1, 2020 at 11:53 PM Alain Hebert <aheb...@pubnix.net> wrote:
>> 
>>    As a coincidence...  I was *thinking* of moving a 90TB SAN (with 
>> mechanical's) to another rack that way...  skateboard, long fibers and long 
>> power cords =D
>> 
> 
> well, what you REALLY need is one of these:
>  https://www.cru-inc.com/products/wiebetech/hotplug_field_kit_product/
> 
> and 2-3 UPS... swap to the UPS, then just roll the stack over, plug to
> utility and done. (minus network transfer)

Reply via email to