> Postmortem and lessons learned for Linaro's release 2013.03
>
> https://wiki.linaro.org/Cycles/1303/Release/Review
>
>
> Highlights and Key Successes
> ============================
> http://www.linaro.org/downloads/1303
>
> http://wiki.linaro.org/Cycles/1303/Release#Release_Information
>
>
> Blueprints
> =========
> The number of high or essential priority blueprints that missed the cycle:
> Android  4 out of 12
> Developer Platform 4 out of 5
> Infrastructure 1 out of 5
> Lava  4 out of 7
> Total  13 out of 29
>
> 45% of high or essential priority blueprints scheduled for this cycle
> were not delivered.
>

This seems high "failure" rate.  Is it typical?

Mark


>
> Total blueprints: 22 out of 45 missed the cycle.
> * Not included is data from the QA team
>
> High priority missed blueprints recap:
> 12.05: 19 out of 48, 39%
> 12.06: 13 out of 31, 42%
> 12.07: 14 out of 31, 45%
> 12.08: 6 out of 26, 23%
> 12.09: 9 out of 28, 32%
> 12.10: 15 out of 38, 39%
> 12.11: 7 out of 19, 37%
> 12.12: not available
> 13.01: 9 out of 28, 33%
> 13.02: 35 out of 69, 48%
>
> * Not included is data from working groups and landing teams
>
> Source:
>
> https://docs.google.com/spreadsheet/ccc?key=0AjEaTwrvj1bidExFWUpKTm1iOURjdkdrdjJsX0JBbWc&usp=sharing
>
> --
> David Zinman, Project Manager
> Linaro.org | Open source software for ARM SoCs
>



-- 
Mark Orvek

mark.or...@linaro.org

VP, Engineering

*M*: +1.408.313.6988 *IRC:* morvek *Skype:* morvek
linaro.org │ Open source software for ARM SoCs
_______________________________________________
linaro-dev mailing list
linaro-dev@lists.linaro.org
http://lists.linaro.org/mailman/listinfo/linaro-dev

Reply via email to