On 19/05/11 14:19, Peter Maydell wrote:
> 
> Sure. As I understand the idea of an agile product backlog, though,
> you don't necessarily do full investigation and planning on every
> item in it (in the way that at the moment we do full down-to-the-work-item
> blueprints for everything at the start of the six months); instead you
> can just do broad back-of-envelope estimates and prioritisations and only
> need to do more detailed planning as things bubble up to the top of the
> backlog.
> 
> -- PMM
> 

The way I see this: It means the backlog items targeted for the next
sprint/month get their work items defined in detail, whereas the
remaining backlog items not yet in the radar, can get only a rough
breakdown to work items. For the not detailed planned blueprints one
should consider flagging any risks which may impede the work early on.

Ideally higher priority items are taken earlier in the cycle, since the
cost of their delay is higher.

What comes to estimating, it ought to happen regularly - for example
before the beginning of a sprint/month. Use ideal/uninterrupted
hours/days for your estimates.

Cheers,

-- 
Ilias Biris,
Aallonkohina 2D 19, 02320 Espoo, Finland
Tel: +358 50 4839608 (mobile)
Email: ilias dot biris at linaro dot org
Skype: ilias_biris