I'm trying to use the taskjuggler exporter for getting an overview of my
project, and it seems to be straight forward if you know a bit about
Taskjuggler.
However, tasks that are scheduled org-mode like, i.e.,
*** TODO My task
SCHEDULED: <2015-01-27 Tue>
don't appear in the report. But, if I add a START property it will appear.
*** TODO My task 2
:PROPERTIES:
:start: 2015-03-01
:END:
I suspect it has something to do with l462-470:
(defun org-taskjuggler-get-start (item)
"Return start date for task or resource ITEM.
ITEM is a headline. Return value is a string or nil if ITEM
doesn't have any start date defined."
(let ((scheduled (org-element-property :scheduled item)))
(or
(and scheduled (org-timestamp-format scheduled "%Y-%02m-%02d"))
(and (memq 'start org-taskjuggler-valid-task-attributes)
(org-element-property :START item)))))
I'm not that experienced in elisp, so I hope someone can help me.
Best regards,
Søren