I typically handle this using the ordered property. -------- * Project :PROPERTIES: :ORDERED: t :END: ** VERIFY Task I am waiting on (I have a TODO state named VERIFY in my normal setup) ** TODO Task I need to do first (after waiting) ** TODO Task I need to do second (after waiting and after the do first) -------
Note that on the VERIFY task I usually also have a person-based tag that tells me who it is that I'm waiting on HTH Mike On Apr 12, 2012, at 11:37 AM, Daniel Krenn wrote: > I have the following situation: In a Project someone else has to do > something and I have to wait until that is finished. If it is finished, > then there are several TODOs. How do I that in a clever way? I.e. how to > write that future TODOs, so that they do not appear as TODOs now (e.g. > in the agenda) but only then, when the status of the project is changed > from WAIT (until the other person has finished) to a state where I have > to do something? > > Daniel >