Hi Patrick,
this sounds reasonable, but I don't currently have time to implement
it. Would be interested in a patch, though.
- Carsten
On Nov 28, 2009, at 7:10 PM, Patrick Drechsler wrote:
Hi Carsten et al,
Carsten Dominik wrote:
On Nov 28, 2009, at 4:51 PM, Patrick Drechsler wrote:
is it possible to skip weekends when rescheduling a task using the
"++1d" operator?
Example:
* TODO work task (not on weekends)
SCHEDULED: <2009-11-27 Fr ++1d>
When changing the state to the DONE state, it will be rescheduled
to the next day, no matter what day of the week that is. So
changing the example above to DONE on a Friday will reschedule the
task for Saturday. Is it possible to reschedule it for Monday?
no, this is not possible currently.
OK, thanks for the quick feedback.
Does this seem like a reasonable feature request?
Regards,
Patrick
_______________________________________________
Emacs-orgmode mailing list
Please use `Reply All' to send replies to the list.
Emacs-orgmode@gnu.org
http://lists.gnu.org/mailman/listinfo/emacs-orgmode
- Carsten
_______________________________________________
Emacs-orgmode mailing list
Please use `Reply All' to send replies to the list.
Emacs-orgmode@gnu.org
http://lists.gnu.org/mailman/listinfo/emacs-orgmode