I find it helps if I can block out certain portions of my calendar
to complete
certain sub-tasks. In other words, I like to look at my agenda for
the day and
know that I should complete, say, sub-task A between 10-12.
I have tried the following:
** TODO Main Task [0/2]
DEADLINE: <2008-06-17 Tue>
- [ ] Sub-task A SCHEDULED: <2008-06-16 Mon 08:00-10:00>
- [ ] Sub-task B SCHEDULED: <2008-06-17 Tue 10:00-12:00>
The result is close to the desired behavior, but the agenda view displays the
title for the MAIN task:
Monday 16 June 2008
todo: 8:00-10:00 Scheduled: TODO Main Task [0/2]
Tuesday 17 June 2008
todo: 10:00-12:00 Scheduled: TODO Main Task [0/2]
I would prefer to see the title of the specific SUB-TASK in the agenda view.
Like so:
Monday 16 June 2008
todo: 8:00-10:00 Scheduled: TODO Sub-task A [0/2]
Tuesday 17 June 2008
todo: 10:00-12:00 Scheduled: TODO Sub-task B [0/2]
Is there a way to achieve this?
thanks.
Try making Sub-tasks A and B TODO items. Doesn't that do more or less
what you want? (It won't show the sub-tasks as [0/2], but then that
wouldn't be accurate---neither sub-task has 2 components.)
Best,
Brian vdB
_______________________________________________
Emacs-orgmode mailing list
Remember: use `Reply All' to send replies to the list.
Emacs-orgmode@gnu.org
http://lists.gnu.org/mailman/listinfo/emacs-orgmode