More observations:
With a test task like this:
* TODO Test
SCHEDULED: <2008-03-25 Tue ++1w>
If I try to mark it DONE on 2008-03-24, i.e. before the scheduled day,
auto-jump does not work either.
Wanrong
Wanrong Lin wrote:
Hi,
With a test task as following:
* TODO A test
SCHEDULED: <2008-03-24 Mon ++1w>
If on the scheduled day (today) I do a "C-c C-t" trying to mark it
"DONE", the scheduled time does not jump to the next occurrence.
However, If I change the task to
* TODO A test
SCHEDULED: <2008-03-23 Sun ++1w>
and do the same thing (note I am "past due" now), things work without
a problem.
I am using 5.23a and Emacs 22.1 on Windows.
Thanks a lot for looking into this.
Wanrong
_______________________________________________
Emacs-orgmode mailing list
Remember: use `Reply All' to send replies to the list.
Emacs-orgmode@gnu.org
http://lists.gnu.org/mailman/listinfo/emacs-orgmode