Juergen,

Based on above proposed translation deadline and referring the principle in
4.0 release schedule, I have listed below checkpoints as 4.0.1 release
schedule in wiki, could you please check and I will correct in wiki for any
inaccuracy.
08/05 - 09/06 bugfix and stabilization, no feature development
08/05 - 09/06 translation
08/26 - 09/13 bugfix verification and regression testing on related areas
09/16 RC1
09/23 RC2
09/27 GA

Regards,
Yu Zhen


On Wed, Aug 14, 2013 at 4:49 PM, Jürgen Schmidt <jogischm...@gmail.com>wrote:

> Hi,
>
> it seems that besides new languages some communities are working on
> fixes/improvements of the existing translation which is fine for me.
>
> To coordinate this work with the rest I would like to propose a general
> translation deadline for new languages as well as updates of existing ones.
>
> I propose September 6th, 2013 - 12:00 UTC at noon
>
> Please take this date into account of any translation related planning.
> Changes after this date won't make it into AOO 4.0.1 and the earlier you
> have finished the work the better it is and you will have more time for
> testing and potential further fixes.
>
> The general workflow is to create an issue, assign it to me and request
> the showstopper flag. When the translation is ready put a comment in the
> issue to signal that it can be integrated.
>
>
> Thanks
> Juergen
>
> ---------------------------------------------------------------------