Hi Thomas,

> -----Original Message-----
> From: dev <dev-boun...@dpdk.org> On Behalf Of Thomas Monjalon
> Sent: Friday, May 15, 2020 5:14 PM
> To: dev@dpdk.org
> Cc: Yigit, Ferruh <ferruh.yi...@intel.com>; Mcnamara, John
> <john.mcnam...@intel.com>; O'Hare, Cathal <cathal.oh...@intel.com>;
> as...@mellanox.com; jer...@marvell.com; hemant.agra...@oss.nxp.com;
> honnappa.nagaraha...@arm.com; david.march...@redhat.com;
> ajit.khapa...@broadcom.com; arybche...@solarflare.com
> Subject: Re: [dpdk-dev] DPDK Release Status Meeting 14/05/2020
> 
> Hi,
> 
> Please let's discuss the dates for the next release cycle.
> 
> > * v20.08 proposal dates, please comment:
> >   * Proposal/V1:            Tuesday, 16 June 2020
> >   * Integration/Merge/RC1:  Tuesday, 14 July 2020
> >   * Release:                        Friday, 7 August 2020
> 
> I prefer a target at the very beginning of the month, it is an insurance 
> against
> disaster, and it may allow a quiet August month for the maintainers.
> 
> Another issue is the delay between -rc1 and final release.
> The above proposal has only 24 days -rc phase.
> Based on records, we need 30 days for a proper -rc phase.
> 
> Taking above requirements into consideration, I propose having a proposal
> deadline earlier by 8 days:
> 
> - Proposal deadline: Monday, 8 June 2020
> - Integration deadline: Tuesday, 30 June 2020
> - 20.08-rc1: Friday, 3 July 2020
> - 20.08-rc2: Friday, 17 July 2020
> - 20.08-rc3: Friday, 24 July 2020
> - 20.08-rc4: Friday, 31 July 2020
> - Release: Monday, 3 August 2020
> 
> 
I think the proposal deadline should be left at Tuesday 16 June, as developers 
have been working towards this date.
I am ok with the other dates.

Regards,

Bernard. 