XenServer 7 support would be an amazing Holiday present.. :)

Regards,
Marty Godsey
Principal Engineer
nSource Solutions, LLC

-----Original Message-----
From: Rohit Yadav [mailto:rohit.ya...@shapeblue.com] 
Sent: Friday, December 16, 2016 10:30 AM
To: dev@cloudstack.apache.org
Subject: Re: 4.8.2.0/4.9.1.0/4.10.0.0 RC Hard Freeze

All,


Given the upcoming holidays, and missed set dates for 4.10.0.0-rc1, we'll be 
unfreezing the master branches to accept few more bugfixes and feature PRs.


I will work with the community towards reviewing, testing and merging few 
useful PRs such as support for XenServer7, the strongswan PR, spring4 migration 
and others. I would be willing to help anyone else take the lead as the RM on 
4.10/master while I'll continue to work towards the next LTS minor release 
(4.9.2.0) that will include some of the useful PRs that could not make into 4.9.


Regards.

________________________________
From: Rohit Yadav <rohit.ya...@shapeblue.com>
Sent: 10 December 2016 08:30:15
To: dev@cloudstack.apache.org
Subject: Re: 4.8.2.0/4.9.1.0/4.10.0.0 RC Hard Freeze

All,


This is declare a hard freeze on 4.8, 4.9 branches, I'll cut RCs for them 
shortly. Master is experiencing some failures, so I'll keep it open until 
Monday (next week) to allow us to include PR 1749 and other bugfixes.


Regards.

________________________________
From: Rohit Yadav <rohit.ya...@shapeblue.com>
Sent: 09 December 2016 13:45:38
To: dev@cloudstack.apache.org
Subject: Re: 4.8.2.0/4.9.1.0/4.10.0.0 RC Hard Freeze

All,


This is a final reminder for PR authors who would like to see their PRs merged 
on 4.8/4.9/master branches need to work with me, fix their PRs and engage/close 
discussions. This weekend, we'll do a final test run on 4.8/4.9/master branches 
before the first RC is cut. Thank you for your contributions.


Regards.

________________________________
From: Rohit Yadav <rohit.ya...@shapeblue.com>
Sent: 08 December 2016 17:35:03
To: dev@cloudstack.apache.org
Subject: 4.8.2.0/4.9.1.0/4.10.0.0 RC Hard Freeze

All,


As shared on the RC status thread, we've only few outstanding PRs that are 
critical for the 4.8.2.0/4.9.1.0/4.10.0.0 releases. We'll have an agreed hard 
freeze on 4.8, 4.9, and master branch at the end of the week. On Monday, 12 
December we'll cut the first set of RCs, test them and only accept blocker 
fixes on the 4.8/4.9/master branches.


Regards.

rohit.ya...@shapeblue.com
www.shapeblue.com<http://www.shapeblue.com>
53 Chandos Place, Covent Garden, London  WC2N 4HSUK @shapeblue




rohit.ya...@shapeblue.com
www.shapeblue.com<http://www.shapeblue.com>
53 Chandos Place, Covent Garden, London  WC2N 4HSUK @shapeblue




rohit.ya...@shapeblue.com
www.shapeblue.com<http://www.shapeblue.com>
53 Chandos Place, Covent Garden, London  WC2N 4HSUK @shapeblue




rohit.ya...@shapeblue.com
www.shapeblue.com
53 Chandos Place, Covent Garden, London  WC2N 4HSUK @shapeblue
  
 

Reply via email to