> Op 4 juli 2016 om 18:17 schreef Rohit Yadav <rohit.ya...@shapeblue.com>:
> 
> 
> I think 4.9 brings some new features, enhancements and improvements that 
> people would appreciate in a LTS release. Many of them cannot be simply 
> backported and 2 weeks will be far shorter to identify, backport and 
> regression-test all those changes.
> 

But that way we keep finding reasons to delay 4.9 and make that the LTS. 4.10 
afterwards will have other cool features, etc. That will stay.

> 
> From my personal experience, I've done a lot of backporting in 4.3, then did 
> maintenance work in 4.5. I think it's still worth it to wait for few weeks to 
> get 4.9.0 out of the door and have LTS based on 4.9.0 release.
> 
> 
> If Will is not able to find time to work on 4.9 release, maybe someone else 
> can takeover and help with the 4.9 release by 15th July (at least get some 
> RCs up for testing and voting)? LTS can be 4.9.1 etc.
> 
> 
> Regards.
> 
> ________________________________
> From: Wido den Hollander <w...@widodh.nl>
> Sent: 04 July 2016 15:32:45
> To: dev@cloudstack.apache.org; John Burwell
> Subject: Re: [PROPOSAL] 2016-2017 Release Cycle and Calendar
> 
> 
> > Op 4 juli 2016 om 6:57 schreef John Burwell <john.burw...@shapeblue.com>:
> >
> >
> > All,
> >
> > Following up on a our discussions about LTS [1], post 4.9 releases [2], and 
> > 5.0.0/6.0.0 [3], I have assembled a release plan for the next 18-20 months 
> > in the wiki [4].  My original proposal assumed by that 4.9 would be 
> > released by 1 July.  I have adjusted the timelines assuming that we will 
> > complete the release by 15 July.  My thinking is that the number of defect 
> > fixes present in 4.9 and 4.8.1 would require more than 2 weeks of work to 
> > backport to a 4.8-based LTS.  Therefore, I have shifted the LTS cutoff 
> > dates from 1 Jan and 1 July to 15 Jan and 15 July.
> >
> > Once we gain consensus on the release cycle and calendar, I will cleanup 
> > the wiki to move completed release plans to an archive area and remove 
> > obsolete release process documentation.
> >
> 
> Looks good to me. It's time that 4.9 is released and shifting to July 15th 
> looks good.
> 
> Overall your release schedule proposal looks good to me, so I'd say +1 on the 
> proposal.
> 
> Wido
> 
> > Thanks,
> > -John
> >
> > [1]: http://markmail.org/thread/zzrjldiryhy3ygfk
> > [2]: http://markmail.org/thread/7rv3jwz4hzf3yplf
> > [3]: http://markmail.org/thread/c24hvshz3z4babjb
> > [4]: 
> > https://cwiki.apache.org/confluence/display/CLOUDSTACK/%5BPROPOSAL%5D+2016-2017+Release+Cycle+and+Calendar<https://cwiki.apache.org/confluence/display/CLOUDSTACK/[PROPOSAL]+2016-2017+Release+Cycle+and+Calendar>
> >
> > john.burw...@shapeblue.com
> > www.shapeblue.com<http://www.shapeblue.com>
> > 53 Chandos Place, Covent Garden, London VA WC2N 4HSUK
> > @shapeblue
> >
> >
> >
> 
> rohit.ya...@shapeblue.com 
> www.shapeblue.com
> 53 Chandos Place, Covent Garden, London  WC2N 4HSUK
> @shapeblue
>   
>  
>

Reply via email to