On Wed, Jul 17, 2013 at 11:43:49PM +0000, Animesh Chaturvedi wrote:
> 
> Folks
> 
> We have an upgrade path from CCP 3.0.2 to 4.0 ACS and since then we have 
> diverged. I would like to propose adding upgrade path from later CCP versions 
> to ACS 4.2 which provides customers the choice to move to ACS from CCP and 
> also brings CCP closer to upstream ACS releases.
> 
> The proposed upgrade paths are CCP3.0.4, CCP3.0.5, CCP3.06, CCP3.0.7 to 
> ACS4.2. Please provide your feedback.
> 
> Thanks
> Animesh
> 
> 
> 
>

Generally...  +1000.  I think that this is a wonderful idea.

I have a couple of thoughts:  

We will really need to implement the "checkpoint"
version concept that Hugo proposed earlier [1].  The reason that I say
this, is that the source and binaries for CCP aren't available to
non-customers of citrix / non-citrix devs.  

I obviously assume that Citrix is officially OK with this (and you are
basically representing that to the list).  Given that "ok", I further
assume that Citrix employeed engineers would do the work (since they
have access to the CCP releases).

Once the upgrades are in ACS, we would want to reduce the testing effort
around them going forward by ensuring that the targeted ACS release that
we test the upgrades to will be one of the "checkpoint" releases per
Hugo's proposal.

Last thought...  this doesn't seem like a 4.2 change to me.  Isn't it
too late to deal with testing it now?  If not, and there are people
ready to roll, then no worries.  I'm just pointing out what may be
obvious:  you've hit feature freeze, and this seems like a significant
amount of work.

-chip

[1] http://markmail.org/thread/p34jbalr25pwocez

Reply via email to