Based on the community discussions of having 4 month cadence I am proposing the 
following schedule:

=============================
 4.2 detailed schedule proposal:
 =============================


 2013-05-31
   Feature Freeze
   All new feature need to have been merged into master by this date.
   Release branch will be cut on this date.
   Jenkins updated to include new release branch builds.
 
 2013-06-01 through 2013-06-30
   Testing/Bug Fixes (testing against jenkins artifacts)
   Documentation Finalization
 
 2013-06-30
   Docs Freeze (except release notes and translations)
   Release Branch moves to limited updates only (only commits allowed
 in would be release blockers fixes, translation updates, etc...)
 
 2013-07-01 through 2013-07-22
   Translation Development and Integration (should be ongoing, but
 focused effort)
   Final regression testing / bug fixes / doc fixes
 
 2013-07-22
   4.2.0-RC1 is created, and project level VOTE is called


I want to call out my concern on technical debt we have accumulated so far.

 I did an analysis on JIRA bugs yesterday night PST on "Affects Version = 4.1" 
and created since Dec 2012 

Total records : 429
Resolution Type (Invalid, Duplicate, Cannot reproduce etc.) : 87 (30 Blockers, 
27 Critical, 27 Major, 4 Minor)
Valid Defects  : 429-87= 342
Fixed : 246 (60 Blockers, 70 Critical, 99 Majors) out of which 217 were fixed 
since Feb
Unresolved : 96 (1 Blocker, 8 Critical, 64 Major)

With this data it looks like we have fixed 2/3 of valid defects in little over 
2 months and pretty much deferring around 1/3 rd of issues for future release.

I also looked at overall backlog of bugs (Critical, Major and Blockers only)  
as of 4/10/2013 - 10:0PM PST. 

284 open (18 Blocker, 38 Critical, 228 Major) ; 
By Fix version
        -  Release 4.0.x and prior: 13
        -  4.1: 70
        -  4.2 : 97
        -  Future: 8
        -  No version: 107

Looking at that we fixed 217 bugs in roughly 2 months during 4.1 cycle,  fixing 
the backlog of bug  will probably take us 2 months.  Should we extend the 4.2 
test cycle by 2 months [Original Schedule: 6/1 - 7/22, Extended Schedule: 
6/1-9/22] to reduce the technical debt significantly? I would like to hear how 
community wants to address technical debt. Based on the input and consensus I 
will publish the agreed schedule next week.


Thanks
Animesh