> -----Original Message-----
> From: Chip Childers [mailto:chip.child...@sungard.com]
> Sent: Tuesday, March 05, 2013 8:09 AM
> To: cloudstack-dev@incubator.apache.org
> Subject: Re: [QUERY] Resolving JIRA ticket when sub task tickets are present
>
> On Tue, Mar 05, 2013 at 10:42:23AM +0530, Sateesh Chodapuneedi wrote:
> > Looking for best practice to follow when resolving a feature ticket in ASF
> JIRA.
> > If a feature branch has QA and DOC sub task tickets which are still open and
> development is complete, should the feature ticket kept open or
> resolved/fixed?
> > Or create another sub task for development mark that sub task as
> resolved?
> > Kindly suggest.
> >
> > Regards,
> > Sateesh
> >
>
> IMO, we would create a "dev" sub-task and track completion of the code
> there. The parent should stay "in progress" until all sub-tasks are done.
[Animesh>] Agreed. Let's follow that for 4.2.
>
> If we don't do child development tasks, then I would still keep the parent as
> "in progress" until docs and QA are done. The feature isn't
> *done* until it's tested and documented.
>
> -chip