Hi Selva.

After a volumen reachs a 0% of use by some process like reclamation, its
status is set pending.  Reuse delay indicates number of days tha a volumen
keeps status pending. After, volume will be a scratch tape again.

Regards

Raul Giraldo Suarez
TSM Bancolombia




"Selva, Perpetua" <[EMAIL PROTECTED]>@VM.MARIST.EDU> con fecha
03/10/2000 12:24:32 PM

Por favor, responda a "ADSM: Dist Stor Manager" <[EMAIL PROTECTED]>

Enviado por:   "ADSM: Dist Stor Manager" <[EMAIL PROTECTED]>


Destinatarios: [EMAIL PROTECTED]
CC:

Asunto:   Re-use Delay


Can someone please explain to me how this parameter works and is this
connected somehow to the no.of versions kept in the database..?

Thanks in Advance