On Tue, 2019-05-07 at 08:00 -0700, akuster wrote:
> > Key Status Links for YP:
> > https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status
> > https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule
> > https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features
>  
> Don't we need 2.8 now ? 

We do, this was on the agenda for the 2.8 planning meeting. We need
dates for the milestones, I'm proposing we use:

M1 Apr. 29, 2019 to June 21, 2019
M1 RC1 June 9th
M2 June 10, 2019 to July 26, 2019 
M2 RC1 14th July
M3 July 15, 2019 to Sept. 6, 2019 
M3 RC1 25th Aug
M4 Aug. 26, 2019 to Oct. 25, 2019
M4 RC1: 30th Sept
M4 RC2: 7th Oct
M4 RC3: 14th Oct 

I updated this into:

https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule

If anyone foresees any problems with this or has any other feedback on
the dates please let us know!

Cheers,

Richard

-- 