On 02/27/2017 08:59 AM, Jolley, Stephen K wrote:
Current Dev Position: YP 2.3 M3
Next Deadline: YP 2.3 M3 by Feb. 27, 2017
*** FEATURE FREEZE for 2.3 is now in effect. ***
SWAT team rotation: Anibal -> Todor on Feb. 24, 2017.
SWAT team rotation: Todor -> Tracy on Mar. 4, 2017.
https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
·We’re now into feature freeze for 2.3.
·We need to decide which recently submitted items should be merged.
Some major items In particular:
orpm v4/dnf to replace rpm v5/smart?
IMHO, we should include dnf in 2.3 so folks can start playing with it
and remove smart in 2.4.
oMerging go into OE-Core?
oSeparate out elderly GPLv2 into a separate layer?
yes, but maybe not for 2.3 if its a large effort.
oGraphics stack vulkan changes?
The "Go" changes hit before the vulkan. Both should have the same rules
applied which ever way the decision goes.
oLarge queue of wic changes?
I am leaning towards trying to take these even if they do delay the M3
release slightly as we do have some time left in M4 to stabilize.
·Unfortunately we continue to have stability issues in testing. There
appear to be some intermittent failures which have crept into master
and M3 merging will likely be delayed until those issues have been
tracked down. They seem to affect sdk image size, breaking the 4GB
limit and eSDKs stopping containing libxml2 under unknown
circumstances, possibly amongst other issues.
·YP 2.2.1 has been released
thanks to all that help.
Proposed upcoming dot releases:
YP 2.1.3 Cut off May 15, 2017
YP 2.1.3 Release by May 26, 2017
YP 2.2.2 Cut off May 29, 2017
YP 2.2.2 Release by June 9, 2017
I like the dot release schedule. Helps me focus.
kind regards,
Armin
Key YP 2.3 Dates:
YP 2.3 M3 Cutoff is Feb 27, 2017
YP 2.3 M3 Release is Mar. 10, 2017
YP 2.3 M4 Cutoff is April 10, 2017
YP 2.3 M4 Release is May 5, 2017
Tracking Metrics:
WDD 2747 (last week 2682)
(https://wiki.yoctoproject.org/charts/combo.html)
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.3_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.3_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.3_Features
[If anyone has suggestions for other information you’d like to see on
this weekly status update, let us know!]
Thanks,
*/Stephen K. Jolley/**//*
*Yocto Project Program Manager*
*INTEL, MS JF1-255, 2111 N.E. 25th Avenue, Hillsboro, OR 97124 *
(*Work Telephone*: (503) 712-0534
(*Cell*: (208) 244-4460
* *Email*:_stephen.k.jolley@intel.com_
--
_______________________________________________
yocto mailing list
yocto@yoctoproject.org
https://lists.yoctoproject.org/listinfo/yocto